Select container from E.C > Take “Full Containers” Only > Make Recap of ETD vs Group code > Select ETD within 3 days from today > Control Modified > Group code > Update to “x1x” ( This is to prevent boxes going to Dumping block )
Select all in E.C > Make Recap of Services vs Allocation Filter ( in order to divide boxes of for different part of terminal )
After segregating the terminal > Choose the service to be planned > for this example is NZ1
Compulsory Recap and Things to have before start Plan :
Recap of services choose > Make Recap
1. Move Hour vs Yard Block ( This recap is use to monitor the movement while planning and to decide as based on the move hour on how many block required )
2. Section factor vs POW ( This recap use to segregate the section factor and considering from which POW the boxes coming in
3. Yard allocation of the service to be planned
4. The Satellite view of the service in the yard
Factor to consider before start planning the discharge:
The overall view of the service in the yard
The choice of block to discharge the boxes
Always start the plan with section factor with the highest volume